Frontier Mall will begin a $3 million dollar paving project beginning on Monday, April 2nd. The project will provide a new surface to the mall's 2,700 space parking lot, as well as inner and outer access roads.

Frontier Mall General Manager Joan Ghani says work will be done in 15 phases. Each phase will include 2 to 3 areas of the parking lot, but the schedule allows portions of the parking lot to be resurfaced in scattered areas. This will allow the project to not affect any large portions of the parking lot at one time. The outer ring road will remain open during the construction of the parking lot phases. Ghani says local contractor Simon will be doing the work.